Local News

Temporary road closure Stanton Harcourt and Standlake 20th and 21st March 2024

Road Works: 20th/21st March

29th February 2024

There will be a temporary road closure at Stanton Harcourt and Standlake, A415 on the 20th and 21st March.

Update on the Parish Council’s working group meeting with SSEN

5th February 2024

A working group of the Parish Council recently met with SSEN to discuss the power issues which have been occurring in the village.   We went through all of the various events and it appears that there have been separate issues at work. These are listed below along with any future works noted.

1. Badswell Lane:

a.      Issue/Cause: The issues in May 2023 were caused by a failure of equipment.

b.      Repair: A generator was provided while the repair was taking place.  This repair has taken place and SSEN believe the substation is in good working order.

c.      Future plans:  The transformer is due to be changed in 2025 and increased in size.

2. Netherton Road:

a.      Issue/Cause: The issues in January 2024 were caused by an increased load.  SSEN can’t determine exactly what caused this, but some elements it could be are new electric car charging points, air source heat pumps, increased usage due to the weather.  It would be the cumulative effect that could have caused this overload.   SSEN did note that properties are fed by a transformer which feeds phases.  These phases don’t go in sequential order, so this would explain why some properties had outages and others didn’t.

b.      Repair: SSEN redistributed the load.  SSEN did note that anyone who has electric car charging points/air source heat pumps/solar panels installed should ensure that their installer has registered them with SSEN so they are aware and can make adjustments accordingly.

c.      Future plans:  We have asked SSEN to let us know of any upgrades on the transformer supporting this area.

3. Park Lane:

a.      Future plans:  The transformer is due to be changed in 2026/2027 and will be increased in size.

4. Ongoing works:  Tree cutting on Fyfield E1: (the large substation that feeds our parish) This work should have been completed in the Summer of 2023.  There are 100 sites outstanding with 38 customers refusing access to their land (not in Appleton with Eaton).  SSEN is working through the legal process to complete these works.

5. Future plans: The overhead network is inspected every 8 years and is next due to be inspected in 2024/2025. Overhead refurbishment is due in 2029/2030.

6.Ongoing works:  Ground mount substations are inspected yearly.  Badwell Lane was inspected on 16/12/2022 and Park Lane was inspected on 3/1/2023.  Both are due to be inspected by February 2024.  

Communication between SSEN and the Parish Council was discussed and we now have direct contact with an SSEN representative for future issues.  However, the Council was pleased to be given the information above to share with residents.

If you do have any concerns, do feel free to contact the Parish Clerk on parishclerk@appleton-eaton-pc.gov.ukor 07767 596 650 and she can raise these with SSEN.   To visit the parish website, go to www.appleton-eaton.org.